|
The evaluation of structural, environmental, and historical elements
of the Moran building and site continues. An EPA-funded Phase II
Environmental Site Assessment is underway, and the Vermont Downtown
Program has provided CEDO a $10,000 grant to conduct geotechnical,
structural, environmental, and wetlands analyses at the Moran Plant
site. |

|
The Vermont Division for Historic Preservation has also provided the
Department of Planning & Zoning a $4,000 grant to complete a historic building
assessment for a complex of ~5 buildings, including the former Moran Generating
Station, associated with public power generation on Burlington’s waterfront.
Results from this work will inform the public debate about the future of Moran.
Completed Reports:
Phase II ESA

Historic Building Analysis

Wetlands Analysis

(These documents are available in PDF format. For the printable PDF
version, you will need
Adobe
Acrobat Reader. If you do not have a current copy of this free
software, you can
download it now.)
Demolition Budget
(This is an Excel document - if you get a request for a password, just cancel and
continue).
- The gross floor area is 44,142 square feet. Building footprint at 96’
elevation (basement) is 16,266 square feet, mezzanine (now in use for
Sailing Center boat storage) is 672 square feet, 102’ elevation has 2016
square feet of usable floor area, and 102’8” elevation has another 506
square feet;
- The site is approximately 2.8 acres in size;
- The entire structure on a thick, reinforced concrete “mat” well beneath
lake level;
- The building is structurally sound and overbuilt for adaptive re-use;
- The roofs could support and be adapted for new upper story construction;
- The exterior steel on North side could also support new construction;
- The first level of the building is at 96’ elevation, below mean lake
level;
- Demolition cost estimates for entire building range from $250,000 to
$600,000;
- Asbestos and pigeon guano remediation is necessary before any work can
be performed.
- It was built to allow lake water into the building via two sheetpiled
sluiceways from the building to the lake.
- Inside the building, an extensive array of underslab chambers below
water level provided water for the coal-fired boilers and cooling of the
various components of the generators.
- Most of interior space on the main floor features ceiling heights of
approximately 20 feet and few columns to impede its use.
- The building has a relatively large level land area surrounding it that
is undeveloped in comparison with other waterfront properties.
Past appraisals have ranged from $600,000 to $1.6 million. The lower values
reflect the impact of Public Trust which prevents uses that could draw
significant income (hotel, private marina etc.), the higher value was calculated
at an earlier date when Public Trust was not an issue. Assigning a real estate
“value” to Moran is problematic. In the absence of significant supplemental
funding, the building has limited commercial value as it cannot be developed
into a private use (Public Trust restrictions), and the per square foot cost of
rehabilitation is cost-prohibitive for a public facility. At the same time, a
building with such a large amount of square footage, close proximity to the
water, and of such height could not be replicated under today’s zoning codes and
design review criteria. Therefore the building’s size and location can be seen
as adding value for a potential developer, but can be offset by the sheer volume
of work required to bring the building up to code.
CEDO hired a professional estimator, MERKUR Construction, to revisit the
issue of potential demolition of the site and for post-demolition estimates of
basic park amenities. This is in response to feedback received in the
Moran Public Forums, where the issue of demolition costs was widely discussed.
You can view the details
here. (This is an Excel document - if
you get a request for a password, just cancel and continue.)
The cost will vary based on cost of the disposal of specific materials, the
method of demolition (deconstruction vs. complete demolition) and how much of
the foundation would be left in-ground. This estimate does not include
retirement of the $376,310 debt owed to Burlington Electric.
The Park construction estimates were provided by SE Group, a Vermont
landscape Architecture firm with many years of experience, and the Parks and
Recreation Department. These estimates were reviewed by City staff.
| Moran Demolition Estimate ( as
of 11/14/07) |
Totals |
| General Demolition Budget (to one foot below grade)
|
$1,554,999 |
| Demolition of concrete tunnels and foundations |
$489,325 |
| Payoff debt on the property |
$376,310 |
| Sub-total demolition |
$2,420,634 |
| Park Construction Estimate
|
|
| Infrastructure (similar to Waterfront Park
amenities) |
$1,898,598 |
| Skate Park |
$375,000 |
| Parking |
$1,500,000 |
| Sub-total for park construction |
$3,773,598 |
| Total |
$6,194,232 |
This estimate does not include a new facility for the Community Sailing
Center.
This scenario is unlikely to qualify for significant federal funding, and the
costs would be borne by the citizens of Burlington. It creates ongoing
operations and maintenance costs for the Parks and Recreation Department without
a source of revenue. This scenario would not generate new tax revenue for the
City.
To view a letter from Recycle North regarding deconstruction, click
here.
The Highest and Best Use for Moran was determined by an appraiser as “public
facilities for recreation and/or assembly”. Public Trust factors and the
location of Moran adjacent to City-owned land contributed to this determination.
The building was completed in 1954, making it over 50 years old: a threshold
that triggers the inquiry into historical significance. Any changes to the
building will require sign-off from the Department of Historic Preservation. An
Historical Buildings
Analysis (completed by New England Preservation Collaborative and funded by
the Vermont Division of Historic Preservation and Vermont DCA), examines the
history of power generation in Burlington and the historic values of several
structures, including Moran.
(This document is available in PDF format. For the printable PDF
version, you will need
Adobe
Acrobat Reader. If you do not have a current copy of this free
software, you can
download it now.)
Despite the current rough appearance of the exterior, the Moran Building has
some outstanding interior features: a huge interior atrium with outstanding
brickwork, overbuilt interior concrete and steel superstructure, and a view from
the roof that cannot compared to any other location on the waterfront.
Unfortunately, the poor condition of the windows and roof parapets on the
building, close proximity of the Burlington Electric substation, the rusted
steel on the north exterior wall, and a long history of clutter, graffiti, and
neglect lead to a generally negative public view of the building as having
aesthetic potential.
Estimates for restoring the building for legal occupancy range from $500,000
for a de minimus upgrade to a viable, clean and weather tight shell to $2.5
million for a heated space with some interior improvements, basic utilities,
plumbing etc. These options would include interior cleaning, roof repair,
carpentry, dewatering and filling basement with compacted gravel to create a
level fist floor, sprinkler system, and the installation of the most basic
utilities, lighting, and window treatments.
|
The building is structurally sound, however a detailed analysis based on any
proposed end-use of the building would need to be performed. Utilities and
services to the site would need to be redesigned and installed before occupancy.
|

|
The challenges of using space effectively in the building are
enormous. Structural elements are an impediment to creating large open
areas in the interior; there are a number of different levels in the
building, all with significant access issues, and there would likely be
limitations on exterior design changes. However, there have been several
rounds of excellent designs crafted that take advantage of this unique
building, showing that these issues can be resolved.
The “Waterfront Enterprise West” designation allows for a broad range of
uses, including those that have been contemplated past proposals for Moran
redevelopment.
Despite the fact that Moran is an existing structure, a new use would require
a new evaluation of parking requirements. The Sailing Center is permitted with
31 spaces, having received a waiver that assumes that the Waterfront Park lot
would accommodate most parking requirements.
Under Public Trust, there is no opportunity for commercial development: the
use must be shown to have public benefit. Specifically: “indoor or outdoor
parks and recreation uses and facilities including parks and open space, marinas
open to the public on a non-discriminatory basis, water dependent uses, boating
and related services” are allowable uses under Public Trust. A restaurant or
small retail operation could be permitted as an ancillary use, but must be
strictly in support of a use permitted under Public Trust.
The Moran is in the so-called “Interim Development Area” (IDA), and is
eligible for redevelopment. The Public Trust Doctrine, while applied to all
filled lands on the waterfront, delineates two areas:
- the “Urban Reserve”, a roughly 40-acre open parcel north of the Moran,
set aside for future generations to determine it’s use, and
- the “Interim Development Area”, a smaller parcel encompassing the Skate
Park, Coast Guard, Fishing Pier, Water Department, Moran Plant, and vacant
areas adjacent to the bike path. The north boundary of the IDA is several
hundred feet north of the Moran Plant, and the filled lands north of this
line is the Urban Reserve.
|